Most of the existing methods uses installation of strut and using the strut to push, but Korea E&C's technology pulls from each side to improve construction and cost.
At the demolition site of an existing building Restoration of the building right before it is about to be torn down
Restoration of the building right before it is about to be torn down
In the case of a building tilting or settling, the safety and usage of the building is at risk. Korea E&C uses jack pile to transform a building that was in E grade to the top
Be happy with Korea E&C Problem solved on an area where the concrete stake equipment could not go through the layers
Construction examples
Pisa Apartment in Incheon 2013. 04 ~ 05
Kwangju Pisa Apartment 2006. 09 ~ 11
Busan exclusive industrial zone gas station 2009. 06 ~ 07